Cornus Oakleigh December Update

Cornus Oakleigh December Update

As we step into the final months of the year, we are excited to bring you the latest updates on the progress of our Cornus Oakleigh project. The construction site has been abuzz with activity and we are proud to share significant milestones achieved during the months of November and December.

Level 1 and Level 2 Suspended Slab Fully Poured:

  • The construction team has successfully poured the suspended slabs for both Level 1 and Level 2, marking a crucial step forward in the vertical development of the project.

Level 1 & Level 2 Columns and Panels 100% Placed:

  • All columns and panels for Levels 1 and 2 have been meticulously placed, ensuring structural integrity and laying the foundation for the upcoming phases.

Basement Blockworks 50% Completed:

  • Progress in the basement blockworks has reached the halfway mark, emphasising our commitment to quality construction from the ground up.

Service Rough-In Commenced in Basement:

  • The installation of essential services, such as electrical, plumbing and mechanical services,  in the basement has begun, setting the groundwork for the functional aspects of the building.


Looking ahead into the next few weeks and as we usher in the new year, our construction agenda remains dynamic and focused on achieving key milestones:

Pour Suspended Slab for Levels 3 to Level 5 and Place Columns and Panels:

  • The upward momentum continues as we progress with the suspended slabs pouring for Levels 3 to 5, accompanied by the placement of columns and panels to solidify the structure.

Basement Blockworks:

  • The completion of basement blockworks is a top priority, underscoring our dedication to a robust and durable foundation.

Basement Service Rough-In:

  • Services in the basement will undergo further installation and refinement.

Internal Framing to Start on Ground in Apartment Building:

  • As we move vertically, internal framing on the ground floor will commence, shaping the interior spaces of the structure.

Window Install to Start:

  • The installation of windows is set to begin, marking a significant aesthetic and functional enhancement to the building envelope.

As we navigate through these next phases, rest assured that our commitment to excellence in construction and project delivery remains unwavering. We extend our gratitude to the community for their ongoing support and look forward to sharing further updates as the Cornus Oakleigh project continues to take shape. If you're interested in purchasing an apartment within this project, now is the time to act, as we are already 70% sold and you can still capitalise on the off-the-plan stamp duty savings, fill in the form below or call 1800 267 687.

 

 

*Please refer to the Federal and State Government websites for further information. Terms and Conditions apply to any other promotions that may be contained within this communication. Please enquire within and check with the vendor and agent for further terms and conditions. Only one promotion can be used per purchase and can not be used in conjunction with any other promotions. The information contained herein is given for general information purposes only and it is subject to change. Readers, viewers and consumers are advised to perform their own research and investigations and obtain their own financial, legal and other advice. The information and materials do not form any representation by any vendors or agents of any vendors and may include third-party opinions that do not represent the opinion of any vendor or agent. They do not form part of any contract of sale and they do not constitute legal, financial, real estate or other advice and must not be regarded or relied upon as such. No warranty is given either expressly or implied and the vendors or agents do not assume liability for negligence or otherwise with respect to the contents herein. Any plans are yet to have had their structural and services review so are subject to change prior to completion of construction. All plans, dimensions, areas and particulars herein whether by measurements or visual representation are approximate only, for general information only, and do not constitute any representation by the vendor or its agents or representatives. They do not form part of any contract of sale. Changes will undoubtedly be made during development and dimensions, fittings, finishes and specifications are therefore subject to change. Any furniture, goods and chattels depicted in this document are not included with any sale. Prospective purchasers or lessees are advised to not to rely on the information contained herein and to satisfy themselves as to the accuracy of all information given by making their own inspections, searches, inquiries and advises or as is otherwise necessary. The vendor or its agents or representatives will not be responsible for any error or misdescription which may appear. Further, the vendor or the developer or their agents or representatives do not represent, warrant and/or guarantee that the integrity of this communication has been maintained or that the communication is free of errors, virus, interception or interference. Usage of this or any other websites and materials and any associated website or material is subject to further terms and conditions.

Cornus Oakleigh September Update

Cornus Oakleigh September Update

We are delighted to share the progress achieved during the past month at the Cornus Oakleigh site.

Read More
Cornus Oakleigh February Update

Cornus Oakleigh February Update

We are delighted to share the latest progress update on the Cornus Oakleigh project. Over the past month, our dedicated team has achieved significant...

Read More
Cornus Oakleigh October Update

Cornus Oakleigh October Update

As spring breathes life and colour into the trees and blossoms, the Cornus Oakleigh site continues to be a hive of activity. With October comes...

Read More