January Construction Update: Cornus Oakleigh Project

January Construction Update: Cornus Oakleigh Project

We are thrilled to bring you the first update of 2024 on the construction progress at Cornus Oakleigh. As we forge ahead with the development of this exceptional residential endeavour, bringing our residents one step closer to their new homes. 

 

In recent weeks, significant milestones have been achieved at the Cornus Oakleigh Project. The construction team successfully poured suspended slabs for Levels 1 and 2 whilst also expertly placing precast columns and panels on Levels 1, 2, and 3 further solidifying the structural foundation of the building. The blockwork milestones are evident, with the basements' blockworks fully completed and ground-level blockworks impressively at 70% completion.

 

Atkinson_st_progress
Dalgety_st_progress

 

The dedication to comprehensive infrastructure is underscored by the 75% completion of the rough-in for high-level services in the basements. Additionally, the project is fortifying against the elements, as external waterproofing has been initiated on the ground level. 

oakleigh_columns
oakleigh_level_3

 

These accomplishments pave the way for the forthcoming weeks, where the focus will shift to pouring suspended slabs for levels 3 to 5, placing precast columns and panels, completing ground-level blockworks, advancing apartment services rough-in, continuing external waterproofing efforts, initiating apartment internal framing, and commencing apartment window installation and exterior finishes and materials are installed. 

 

As these elements seamlessly come together, the Cornus Oakleigh project continues to shape into a testament of precision, innovation and quality craftsmanship. Your continued support and patience are greatly appreciated as we bring this visionary project to life.

 

With construction progressing steadily, your chance to capitalise on the off-the-plan stamp duty savings are diminishing. Secure your new home today! Call 1800 267 687 or fill in the form below. We have limited 1, 2 and 3 bedroom apartments remaining. 

 

 

 

*Please refer to the Federal and State Government websites for further information. Terms and Conditions apply to any other promotions that may be contained within this communication. Please enquire within and check with the vendor and agent for further terms and conditions. Only one promotion can be used per purchase and can not be used in conjunction with any other promotions. The information contained herein is given for general information purposes only and it is subject to change. Readers, viewers and consumers are advised to perform their own research and investigations and obtain their own financial, legal and other advice. The information and materials do not form any representation by any vendors or agents of any vendors and may include third-party opinions that do not represent the opinion of any vendor or agent. They do not form part of any contract of sale and they do not constitute legal, financial, real estate or other advice and must not be regarded or relied upon as such. No warranty is given either expressly or implied and the vendors or agents do not assume liability for negligence or otherwise with respect to the contents herein. Any plans are yet to have had their structural and services review so are subject to change prior to completion of construction. All plans, dimensions, areas and particulars herein whether by measurements or visual representation are approximate only, for general information only, and do not constitute any representation by the vendor or its agents or representatives. They do not form part of any contract of sale. Changes will undoubtedly be made during development and dimensions, fittings, finishes and specifications are therefore subject to change. Any furniture, goods and chattels depicted in this document are not included with any sale. Prospective purchasers or lessees are advised to not to rely on the information contained herein and to satisfy themselves as to the accuracy of all information given by making their own inspections, searches, inquiries and advises or as is otherwise necessary. The vendor or its agents or representatives will not be responsible for any error or misdescription which may appear. Further, the vendor or the developer or their agents or representatives do not represent, warrant and/or guarantee that the integrity of this communication has been maintained or that the communication is free of errors, virus, interception or interference. Usage of this or any other websites and materials and any associated website or material is subject to further terms and conditions.

Cornus Oakleigh October Update

Cornus Oakleigh October Update

As spring breathes life and colour into the trees and blossoms, the Cornus Oakleigh site continues to be a hive of activity. With October comes...

Read More
Cornus Oakleigh December Update

Cornus Oakleigh December Update

As we step into the final months of the year, we are excited to bring you the latest updates on the progress of our Cornus Oakleigh project. The...

Read More
April Update- Cornus Oakleigh

1 min read

April Update- Cornus Oakleigh

Over the past month, significant progress has been made at the Cornus Oakleigh apartment project. The windows have been fully installed up to level...

Read More