Glen Iris October Construction Update

Glen Iris October Construction Update

As of October, significant progress has been made at the Cornus Glen Iris construction site. Here are the key updates for the past month and what's to come in November:

 

October Progress:

  • Site Preparation: Site preparation for the crane has been completed. This involves creating the necessary infrastructure to support the crane's installation and operation.
  • Upper Basement Shotcrete Walls: The upper basement shotcrete walls have been successfully completed. 
  • Lower Basement Shotcrete Walls: Similar to the upper basement, the lower basement shotcrete walls have been completed. This marks a significant step in the construction process, providing structural stability to the building's lower levels.
  • Excavation in Basement: The final stages of excavation in the basement are in progress. This excavation is essential for creating the building's foundation and space for utilities.
Glen Iris project excavation activity
Glen Iris project shotcrete retention wall activity
Glen Iris project excavation activity


November Plans:

  • Crane Installation: The crane installation is scheduled to take place in early November. The crane is a crucial piece of equipment for lifting and placing heavy construction materials, its installation will greatly facilitate the ongoing construction activities.
  • Shotcrete to Retention Walls: On Thursday, November 2nd, the last round of shotcrete will be applied to the retention walls of the basement. This step is crucial for ensuring the structural integrity of the foundation.
  • Foundation Work: The crane base has been poured and pad footings and lift core footings are underway. 
  • In-Ground Plumbing: In mid November, it is expected that the construction team is planning to start the in-ground plumbing works, which will include installing stormwater tanks and perimeter drains.
  • Basement Slab: Following the plumbing works, the focus will shift to laying the basement slab. This is a significant step in building the structure's floors and will bring us closer to the construction of above-ground levels.

 

These updates reflect the progress made in October and the planned activities for November at the Cornus Glen Iris construction site. As always, the project team is committed to ensuring a safe and efficient construction process to bring this development to completion. For more information or to register your interest in our Cornus Glen Iris project fill in the form below. 

 

*Please refer to the Federal and State Government websites for further information. Terms and Conditions apply to any other promotions that may be contained within this communication. Please enquire within and check with the vendor and agent for further terms and conditions. Only one promotion can be used per purchase and can not be used in conjunction with any other promotions. The information contained herein is given for general information purposes only and it is subject to change. Readers, viewers and consumers are advised to perform their own research and investigations and obtain their own financial, legal and other advice. The information and materials do not form any representation by any vendors or agents of any vendors and may include third-party opinions that do not represent the opinion of any vendor or agent. They do not form part of any contract of sale and they do not constitute legal, financial, real estate or other advice and must not be regarded or relied upon as such. No warranty is given either expressly or implied and the vendors or agents do not assume liability for negligence or otherwise with respect to the contents herein. Any plans are yet to have had their structural and services review so are subject to change prior to completion of construction. All plans, dimensions, areas and particulars herein whether by measurements or visual representation are approximate only, for general information only, and do not constitute any representation by the vendor or its agents or representatives. They do not form part of any contract of sale. Changes will undoubtedly be made during development and dimensions, fittings, finishes and specifications are therefore subject to change. Any furniture, goods and chattels depicted in this document are not included with any sale. Prospective purchasers or lessees are advised to not to rely on the information contained herein and to satisfy themselves as to the accuracy of all information given by making their own inspections, searches, inquiries and advises or as is otherwise necessary. The vendor or its agents or representatives will not be responsible for any error or misdescription which may appear. Further, the vendor or the developer or their agents or representatives do not represent, warrant and/or guarantee that the integrity of this communication has been maintained or that the communication is free of errors, virus, interception or interference. Usage of this or any other websites and materials and any associated website or material is subject to further terms and conditions.

 
January Update Cornus Glen Iris

January Update Cornus Glen Iris

We are pleased to provide you with the latest progress update on the Cornus Glen Iris project. Our dedicated team has been working diligently to...

Read More
Glen Iris November Construction Update

Glen Iris November Construction Update

The retention phase has wrapped up, and we're gearing up for the structural phase with the installation of the crane now complete. Entering the...

Read More
Cornus Glen Iris March Update

1 min read

Cornus Glen Iris March Update

We're thrilled to bring you the latest update on the Cornus Glen Iris project as we continue to make strides in construction. Over the past four...

Read More